- Prepared
- J. Rivera, Commissioning Lead
- Distro
- Owner Rep, GC, Elec Cx, Mech Cx
| 07:00–11:30 | Functional performance test | PDU-3B-02 |
| 11:30–13:00 | Breaker coordination check | SWBD-2A |
| 13:00–16:30 | Integrated systems prep | GEN-04 |
| 08:00–12:00 | Air handler startup | AHU-2-014 |
| 13:00–16:00 | Chilled water flush | CHW-PMP-01 |